- Northbound U.S. 89 Daytime Lane Closure
- Friday, January 15, from 9:00 a.m. to 2:00 p.m. northbound U.S. 89 will reduced to one lane while crews perform a pavement repair in the 200 North/400 North intersection. Expect some congestion and delay during this activity.
.
FRUIT HEIGHTS – MOUNTAIN ROAD/650 NORTH CLOSURE: Beginning Wednesday, January 13, Mountain Road will be closed at 650 North for Utility work and frontage road reconstruction. Access between U.S. 89 and 675 North will also be closed Area motorists will be detoured to Crestwood Road through mid-February.
- 200 North/400 North New Southbound Exit:
- Access to 200 North/400 North from southbound U.S. 89 will now use the new southbound off-ramp. Motorists traveling from southbound U.S. 89 to westbound 200 North will exit prior to the traffic signal. Please drive with caution.
- Canyon Creek Road:
- Utility crews are installing water lines along the new frontage road alignment and will cross Canyon Creek Road south of the Adams Canyon trailhead. To maintain traffic, crews are building a temporary bypass route around the work zone.
Noise wall installation on the west side of U.S. 89 between Green Road and 200 North/400 North is underway.
- Utility crews are installing water lines along the new frontage road alignment and will cross Canyon Creek Road south of the Adams Canyon trailhead. To maintain traffic, crews are building a temporary bypass route around the work zone.
-
- Gentile Street: Gentile Street is now closed at the west end near 2692 East and the new connection to Gordon Avenue while crews install several utility lines. Residents east of 2692 East should use Woodridge Drive to Oak Hills Drive while those west should use Gentile Street to Oak Hills Drive. Through traffic should use Oak Hills Drive.
-
- Pinewood Lane: Access between Pinewood Lane and U.S. 89 will be closed as part of this shift. This access will not be restored. Area residents should use Mutton Hollow Road as and alternative while Oak Hills Drive is under construction.
OAK HILLS DRIVE INTERSECTION RELOCATION
The U.S. 89 intersection at Oak Hills Drive has been relocated a few hundred feet north of the current location. All movements between U.S. 89 and Oak Hills Drive will be maintained. This traffic configuration is expected to be in place through 2021. Area motorists should anticipate some additional time at traffic signals throughout the project area and plan accordingly.TANGLEWOOD LANE CLOSURETanglewood Drive is closed to U.S. 80 while crews install a 30″ water line and other utilities. U.S. 80 access is being maintained at Corral Drive through the spring. Please drive with caution and follow the posted signs. This traffic configuration is expected to be in place through spring. Tanglewood Drive will reopen to the frontage road when all the utility work is complete in the area.ONGOING CONSTRUCTION ACTIVITIES AND IMPACTS- East Frontage/Utility Work Update: You might have heard that this project is relocating 150 miles of utilities (pipes, cables, wires, culverts, etc.) in order to build the highway. We’re trying to be good neighbors, but this is one of the most impactful parts of any big road project, and we know it is tough on area residents. All year we’ve been closing local road, digging ditches, and working close to homes and we still have more work to do. This video link shows how this process of locating, digging up, and moving these utilities works and why we do it this way.
U.S. 89 Closed to Bicycles and Pedestrians
Shoulder closures along U.S. 89 are now underway. It is no longer safe for bicyclists and pedestrians to walk or ride in the shoulders of U.S. 89. We are asking for your cooperation in keeping everyone safe. When the project is complete the frontage roads will serve as a continuous bicycle route parallel to U.S. 89. Until then, bicyclists are asked to consider alternate routes. The closest parallel route is shown at right. Bicyclists and pedestrians wishing to cross U.S. 89 should use signalized intersections
CONSTRUCTION IMPACTS
Work is ongoing on the frontage roads and shoulders of U.S. 89. Activities include a significant amount of utility relocation, storm drain installation, building demolition and earthwork. The following traffic impacts are associated with these activities:.
TRAFFIC IMPACTS
Throughout construction, two lanes will be maintained in each direction on U.S. 89 during peak travel times. Nighttime and Sunday daytime lane closures are planned. Work will occur around the clock to reduce the overall project duration.
ACCESS
Many of the existing side streets accesses will be permanently closed and traffic rerouted to the interchanges to access U.S. 89. These access points will remain open until the nearest alternate access points are complete. Temporary access will be maintained for properties with direct access to/from U.S. 89.
PROPERTY ACQUISITION
The project team continues to coordinate with affected property owners. All impacted properties and full acquisitions have been identified and the team is working through the list in order of location and construction priority. If you are a property owner on or near U.S. 89, and have not yet been contacted, feel free to contact us. The project design map also details planned impacts to properties and you can also learn more about the overall property acquisition process here.