Project Construction Information |
Expenditures by Category As of 30-JUN-2024 |
Total Expenditures by Funding Source As of 30-JUN-2024 |
|
Source |
Funding |
Expenditures |
Federal |
$176,307,790 |
$171,210,059 |
State |
$4,192,210 |
$4,226,421 |
Local |
$114,643 |
$114,643 |
Report Total: |
$180,614,643 |
$175,551,123 |
| |
Total Project Funding As of 30-JUN-2024 |
|
Fund |
Funding |
Expenditures |
STP_FLX_ST |
$114,215,960 |
$109,118,229 |
STP_BRIDGE |
$12,127,013 |
$12,127,013 |
ST_RET_ROW |
$4,192,210 |
$4,192,210 |
OTHER |
$14,810 |
$14,810 |
NHPP_IM |
$36,264,817 |
$36,264,817 |
NHPP_BR |
$13,700,000 |
$13,700,000 |
LOCAL_GOVT |
$99,833 |
$99,833 |
OTHR |
|
$34,211 |
Report Total: |
$180,614,643 |
$175,551,123 |
| |
|
- Planned |
- Awarded |
- Close Out |
- In Design |
- Under Construction |
- Project Completed |
- Advertised |
- Construction Complete |
- Hold |
|
|